What is an occupation certificate (OC)
An occupation certificate (OC) is the document issued by the local planning authority, such as the BMC in Mumbai, confirming that a building has been built as per its approved plans and can legally be occupied.
The OC in one picture
A building collects three key permissions over its life:
| Stage | Document | What it means |
|---|---|---|
| Before work starts | Building plan approval and commencement certificate (CC) | You may start building, as per these plans. |
| When work is done | Completion certificate | The building has been completed as per the approved plans. |
| Before people move in | Occupation certificate (OC) | The building is fit to be occupied. |
The names and the exact order vary between cities. In Mumbai, the BMC issues these approvals for most buildings.
What the authority checks
Before issuing an OC, the authority checks that the building matches the approved plans and that basic requirements are in place, for example:
- the building follows the sanctioned plans and floor area
- water supply, drainage and sewerage
- fire safety approvals
- lifts, where required
The RERA Act defines the occupancy certificate as the certificate issued by the competent authority permitting occupation of a building, which has provision for civic infrastructure such as water, sanitation and electricity.
Why buyers should care
The OC is the moment a building becomes legally livable. Without it:
- permanent utility connections can be delayed
- some banks will not lend, or will lend less, on the flat
- resale is harder, because the next buyer’s bank will ask for it
- forming the society and getting the land conveyed can be delayed
Why developers care even more
For a developer, the OC is the last big approval, and often the trigger for the final payments from buyers. A project can be fully built and fully sold, and still be stuck waiting for its OC. Planning for it from day one is part of protecting the king: cash flow.
How to check
- Ask the developer for a copy of the OC, or the expected date if it is pending.
- Check the project’s page on the MahaRERA website, where documents and updates are uploaded.
- For a resale flat, ask the society for a copy before you pay a token amount.
Questions people ask
What is the full form of OC in real estate?
Occupation certificate. Some places call it an occupancy certificate. They mean the same thing.
Who is responsible for getting the OC?
The developer. Section 11(4)(b) of the RERA Act makes the promoter responsible for obtaining the completion certificate or occupancy certificate, or both, and making it available to buyers.
What is a part OC?
An OC issued for part of a project, such as some floors or one wing, so that those parts can be occupied while the rest is finished.
How soon must buyers take possession after the OC?
Under Section 19(10) of the RERA Act, a buyer must take physical possession within two months of the occupancy certificate being issued for the apartment.
Is it safe to buy a flat without an OC?
It carries real risk. You may face issues with permanent water and power connections, home loans, resale and society formation. Ask the developer why the OC is pending and when it is expected.
Sources
Rules change. Always confirm on the official source before you act. Checked on 16 November 2026.
- The Real Estate (Regulation and Development) Act, 2016, India Code
- MCGM (BMC), official portal
- MahaRERA, official website
This page explains how things work. It is not legal, tax or investment advice.
Keep reading
- What is real estateThe complete guide, with an India and Mumbai lens.
- What is RERA and MahaRERARERA is the Real Estate (Regulation and Development) Act, 2016, a central law that makes developers register projects, disclose details and keep buyers' money in a separate account, and MahaRERA is the authority that enforces it in Maharashtra.
- How redevelopment works in MumbaiRedevelopment in Mumbai is when an old building is demolished and rebuilt by a developer, who gives the existing members new, usually larger flats at no cost and pays for the project by selling extra flats built using the additional FSI available on the plot.
- Carpet area vs built-up area vs super built-up areaCarpet area is the usable floor area inside a flat, built-up area adds the thickness of the walls and some outside areas, and super built-up area adds the flat's share of common spaces like lobbies and staircases.